Resurrection Creek Aquatic Habitat Maintenance
Restore flow into a constructed side channel by removing accumulated debris/sediment deposited during a 2012 ice dam break flood event. Improve grade control and excavate an additional inlet reducing potential dewatering from future flood events.
Project Summary
Location Summary:
Resurrection Creek four miles upstream from Hope, Alaska
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/15/2014 |
Decision | 04/2014 (Estimated) |
Implementation | 05/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (19), 36 Cfr 220.6(E)(19)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chugach National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Current Status:
Completed
Project Decision Information
Aquatic Habitat Maintenance on Resurrection Creek I Side Channel
Decision Signed Date: 04/13/2014
Forests:
Chugach National Forest
Districts:
Seward Ranger District
States:
Alaska
Counties:
Kenai Peninsula
Legal Land Description:
T9N,R2W,NW Quarter Section 28
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Angela Coleman
161 East 1st Avenue, Door 8
Anchorage, AK 99501
907-288-7728
ajcoleman@fs.fed.us
Last Updated: 7/25/2014