GCI Communications, Corp. is realigning fiberoptic line along MP77.5 and 80.7 Seward Highway.
GCI is proposing to install approximately 750 feet of new fiberoptic line and one new vault between Seward Highway MP77.5 and 80.7 as part of the Seward Highway MP75-90 Road and Bridge Rehabilitation project.
Project Summary
Location Summary:
Mile Post 77.5 and 80.7 Seward Highway
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/17/2021 |
Decision | 05/2021 (Estimated) |
Implementation | 05/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Glacier Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
GCI Communications, Corp. is realigning fiberoptic line along MP77.5 and 80.7 Seward Highway.
Decision Signed Date: 05/12/2021
Forests:
Chugach National Forest
Districts:
Glacier Ranger District
States:
Alaska
Counties:
Anchorage
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Debra Srb
P.O. Box 129
Girdwood, AK 99587
907-424-4726
debra.srb@usda.gov
Last Updated: 6/22/2021