Uinta Express Pipeline Project

The proposed action includes a 12-inch buried carbon steel pipeline approximately 135 miles long and ancillary facilities. Approximately 14 miles of the pipeline would be on the Uinta-Wasatch-Cache National Forest.

Location Summary

The proposed pipeline would cross the UWCNF in the Wolf Creek/Upper South Fork Provo River area of the Heber-Kamas Ranger District, and in the Bountiful Peak area of the Salt Lake Ranger District.

Districts: Salt Lake Ranger District, Heber-Kamas Ranger District

Project Milestones

MilestoneDate
NOI in Federal Register01/22/2014
DEIS NOA in Federal Register01/31/2014
FEIS NOA in Federal Register06/2015 (Estimated)
Objection Period Start08/2015 (Estimated)
Decision03/2016 (Estimated)
Implementation04/2016 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public

https://www.fs.usda.gov/project/uwcnf/?project=43620