Reconstruction Trail #201 and Trail #110 Reroute
Reconstruction of the turnpike along Trail #201 immediately north of the wilderness boundary. The reroute will move the trail #110 from crossing a spring in a riparian area to crossing Biggs Creek in a more rock armored location.
Project Summary
Current Status:
Completed
Location Summary:
Rocky Mountains, The reroute on 110 (trail 201 turns into 110 at cabin creek, it’s the old district boundary) will move the trail from crossing a spring in a riparian area to crossing Biggs creek in
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/24/2012 |
| Comment Period | 05/25/2012 |
| Decision | 06/2012 (Estimated) |
| Implementation | 07/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Rocky Mountain Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Project Decision Information
Reconstruction Trail #201 and Trail #110 Reroute
Decision Signed Date: 06/02/2012
Legal Notice Date: 06/06/2012
Forests:
Lewis And Clark National Forest
Districts:
Rocky Mountain Ranger District
States:
Montana
Counties:
Teton
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ian Bardwell
2880 Skyway Drive
Helena, MT 59601
406-466-5341