Gibson Dam Hydroelectric Transmission Line
Authorization to construct a transmission line within an existing utitlity corridor on the Rocky Mountain Ranger District. This is part of the Gibson Dam Hydroelectric project licensed by FERC in January 2012.
Project Summary
Current Status:
Completed
Location Summary:
South of Gibson Reservoir in the utility corridor located along the Sun Canyon Road.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/09/2006 |
| Comment Period | 05/26/2010 |
| Decision | 06/2013 (Estimated) |
| Implementation | 11/2013 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Nepa Document Prepared By Another Federal Agency
Lead Management Unit:
Lewis And Clark National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Hydropower; Special Use Authorizations
Project Decision Information
Gibson Dam Hydroelectric Project
Decision Signed Date: 06/25/2013
Legal Notice Date: 07/01/2013
Forests:
Lewis And Clark National Forest
Districts:
Rocky Mountain Ranger District
States:
Montana
Counties:
Lewis and Clark; Teton
Legal Land Description:
Sections 2, 3, and 4 T21N, R9W and Sections 34, 35, and 36 T22N, R9W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tessa Donahue
2880 Skyway Drive
Helena, MT 59601
406-791-7710
tessadonahue@fs.fed.us
Last Updated: 8/19/2013