Jimtown Road Conductor Upgrade - 2023 NorthWestern Energy
NorthWestern Energy will rebuild 1 mile of existing powerline within their powerline right-of-way authorized under the special use permit that crosses Jimtown Road off the North East end of Canyon Ferry Lake.
Project Summary
Location Summary:
Northern Big Belt Mountains
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/01/2023 |
Decision | 07/2023 (Estimated) |
Implementation | 07/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lewis And Clark National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Area Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Jimtown Road Conductor Upgrade - 2023 NorthWestern Energy
Decision Signed Date: 07/07/2023
Forests:
Lewis And Clark National Forest
Districts:
Helena Ranger District
States:
Montana
Counties:
Lewis and Clark
Legal Land Description:
T. 11 N, R. 1 W, Sec. 33 & 34
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
John Fennell
2880 Skyway Drive
Helena, MT 59601
406-495-3928
John.Fennell@usda.gov
Last Updated: 7/11/2023