Golden Horseshoe Trail Reconstruction and Road Closure Projects within the Swan River Watershed
Construction of approx. 3.7 mi of non-motorized single-track trail and construction of approx. 5.0 mi of motorized single-track trail. Decommissioning of approx. 5.1 mi of unauthorized roads in the Golden Horseshoe area near Breckenridge.
Project Summary
Location Summary:
Golden Horseshoe area near Breckenridge, CO
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/30/2012 |
| Comment Period | 10/30/2012 |
| Decision | 11/2013 (Estimated) |
| Implementation | 06/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
East Zone/Dillon Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management; Recreation Management; Road Management
Project Activity:
Road Decommissioning; Watershed Improvements
Current Status:
Completed
Project Decision Information
Golden Horseshoe Trail construction
Decision Signed Date: 11/01/2013
Forests:
White River National Forest
Districts:
East Zone/Dillon Ranger District
States:
Colorado
Counties:
Summit
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ken Waugh
680 Blue River Parkway
Silverthorne, CO 80498
970-262-3446
kwaugh@fs.fed.us
Last Updated: 3/1/2023