Indiana Creek Aquatic Organism Passage and Road Decommissioning
To create an Aquatic Organism Passage at the open water ford at the intersection of Indiana Creek and Pennsylvania Creek Rd. The 2nd objective is to decommission a 1.3 mi segment of a non-system FS road that is causing sediment and bank instability.
Project Summary
Location Summary:
Indiana Creek Drainage - SE of Breckenridge
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/01/2019 |
| Decision | 05/2019 (Estimated) |
| Implementation | 05/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (20), 36 Cfr 220.6(E)(20)
Special Authority:
Not Applicable / Other
Lead Management Unit:
White River National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management; Road Management
Project Activity:
Road Decommissioning; Species Habitat Improvements; Travel Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
Indiana Creek Aquatic Organism Passage Project
Decision Signed Date: 05/24/2019
Forests:
White River National Forest
Districts:
East Zone/Dillon Ranger District
States:
Colorado
Counties:
Summit
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ashley Nettles
900 Grand Avenue
Glenwood Springs, CO 81601
970-262-3457
anettles@fs.fed.us
Last Updated: 12/10/2019