Vail Resort 2018 Summer Construction
Vail Resort proposes to upgrade Game Creek Express (Chair #7), install Family Learning Zone Corbels and Photo Stakes, pave a section of trail at Adventure Ridge, install Diesel Exhaust Fluid (DEF) storage tanks and improve Bell's Camp deck.
Project Summary
Location Summary:
Within the current special use boundary of Vail Mountain Resort
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/17/2018 |
Decision | 06/2018 (Estimated) |
Implementation | 06/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
East Zone/Holy Cross Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Vail Resort 2018 Summer Construction
Decision Signed Date: 06/14/2018
Forests:
White River National Forest
Districts:
East Zone/Holy Cross Ranger District
States:
Colorado
Counties:
Eagle
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Max Forgensi
24747 US Highway 24
Minturn, CO 81645
435-636-3335
mforgensi@fs.fed.us