Mountain Parks Electric, INC-Fiber Optic Line
Construction, operation and maintenance of a fiber optic telecommunication line including 1.51 miles of underground cable and 560 feet of overhead cable on an existing electric distribution line right-of-way north of Green Mountain Reservoir
Project Summary
Location Summary:
Existing electric power line along Heeney Road (Summit County Road 30) & north of Green Mountain Reservoir Dam
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/28/2018 |
| Decision | 05/2020 (Estimated) |
| Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
White River National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Mountain Parks Electric, INC-Fiber Optic Line
Decision Signed Date: 05/12/2020
Forests:
White River National Forest
Districts:
White River National Forest All Units
States:
Colorado
Counties:
Summit
Legal Land Description:
Sections 11, 14 and 15, Township 2 South, Range 80 West, 6th PM, Summit County, CO
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Anna Bengtson
900 Grand Avenue
Glenwood Springs, CO 81601
970-262-3454
annabengtson@fs.fed.us