Town of Carbondale - Micro Hydro Generator Project. Amendment to Nettle Creek Water Plant SOP334
Town of Carbondale is requesting to ad a Micro Hydro Generator to the existing water treatment plant at Nettle Creek. The hydroelectric facility is expected to produce approximately 225,000kWh/year.
Project Summary
Location Summary:
Nettle Creek water treatment plant
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/01/2020 |
| Decision | 07/2020 (Estimated) |
| Implementation | 07/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
White River National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Town of Carbondale - Micro Hydro Generator Project. Amendment to Nettle Creek Water Plant SOP334
Decision Signed Date: 07/28/2020
Forests:
White River National Forest
Districts:
East Zone/Holy Cross Ranger District
States:
Colorado
Counties:
Garfield
Legal Land Description:
T9S, R88W, Section 10, 6th Principal Meridian, Garfield County, Colorado
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Carole Huey
900 Grand Avenue
Glenwood Springs, CO 81601
970-945-3219
clhuey@fs.fed.us
Last Updated: 7/29/2020