Snackenburg Creek Project
Project proposes to improve the 47N06Y road where Snackenburg Creek crosses the road to improve aquatic connectivity and reduce the potential for sediment from the road to enter the creek. Water Board Waiver Category B.
Project Summary
Current Status:
Completed
Location Summary:
Approximately 20 miles northwest of Macdoel, CA. Deer Creek-Klamath River 6th field, subwatershed.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/13/2017 |
| Decision | 05/2018 (Estimated) |
| Implementation | 08/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Goosenest Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Watershed Management
Project Activity:
Road Maintenance; Road Improvements/Construction; Watershed Improvements
Project Decision Information
Snackenburg Creek Project
Decision Signed Date: 05/11/2018
Forests:
Klamath National Forest
Districts:
Goosenest Ranger District
States:
California
Counties:
Siskiyou
Legal Land Description:
Township 47 North, Range 4 West, Section 13, MDM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robert Reed
37805 Highway 97
Macdoel, CA 96058
907-874-7558
rmreed@fs.fed.us
Last Updated: 8/21/2018