Baird Springs Pipeline Repair
Replacement of approximately 0.75 miles of deteriorating 1" pipe with 1.5" PVC to an existing trough. Implementation will require digging of a 2' deep ditch in a previously disturbed area. Water Board Waiver n/a.
Project Summary
Location Summary:
The project is located 2.5 miles east of the town of Tennant, CA.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/01/2019 |
Decision | 06/2020 (Estimated) |
Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (9), 36 Cfr 220.6(E)(9)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Goosenest Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Grazing Management
Project Activity:
Grazing Structural Improvements
Current Status:
Completed
Project Decision Information
Baird Springs Pipeline Repair
Decision Signed Date: 06/17/2020
Forests:
Klamath National Forest
Districts:
Goosenest Ranger District
States:
California
Counties:
Siskiyou
Legal Land Description:
Township 43 North, Range 1 East, Sections 9 and 4, Mt. Diablo Meridian.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dani Balin
37805 Highway 97
Macdoel, CA 96058
5303985776
Dani.Sundet@usda.gov
Last Updated: 7/20/2020