Round Mountain Power Line Project
Pacific Gas and Electric Company proposes the construction of a power line to replace a power line line lost in the 2020 August Complex Fire. This power line will supply power to a telecommunications site at Round Mountain.
Project Summary
Location Summary:
The proposed project is in Tehama County within the Mendocino National Forest seven miles Northwest of Paskenta, California
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/28/2022 |
Decision | 03/2023 (Estimated) |
Implementation | 05/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Grindstone Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management; Facility Management
Project Activity:
Electric Transmission; Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance
Current Status:
In Progress
Forests:
Mendocino National Forest
Districts:
Grindstone Ranger District
States:
California
Counties:
Tehama
Legal Land Description:
T24N, R7W, Sec 20,29
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Casey Collins
825 North Humbolt Avenue
Willows, CA 95988
530-934-1148
Casey.Collins@usda.gov
Last Updated: 11/14/2022