Telephone Flat Aggregate Crushing Project
Utilize an existing aggregate material source and develop material stockpiles that will be used to maintain and resurface NFS roads currently open and maintained for motor vehicle travel.
Project Summary
Location Summary:
The project area is located approximately 1.6 miles southeast of Medicine Lake.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/19/2018 |
| Decision | 08/2018 (Estimated) |
| Implementation | 08/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Doublehead Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Current Status:
Completed
Project Decision Information
Telephone Flat Aggregate Crushing Project
Decision Signed Date: 08/27/2018
Forests:
Modoc National Forest
Districts:
Doublehead Ranger District
States:
California
Counties:
Siskiyou
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Bielecki
P.O. Box 369
Tulelake, CA 96134
530-233-8850
csbielecki@fs.fed.us
Last Updated: 8/28/2018