Pine Creek Basin Trailhead Toilet
A new vault toilet at the Pine Creek Basin Trailhead is needed to provide sanitation facilities at this high-use recreation site. The District will install one (1) single-stall vault toilet at the trailhead.
Project Summary
Location Summary:
Pine Creek Trailhead, just west of the South Warner Wilderness, about 16 mi. SE of Alturas, CA.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/15/2021 |
| Decision | 07/2022 (Estimated) |
| Implementation | 06/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Warner Mountain Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Facility Management
Project Activity:
Developed Site Management; Facility Improvements/Construction; Trail Management; Wilderness Management
Current Status:
Completed
Project Decision Information
Pine Creek Basin Trailhead Toilet
Decision Signed Date: 07/25/2022
Forests:
Modoc National Forest
Districts:
Warner Mountain Ranger District
States:
California
Counties:
Modoc
Legal Land Description:
T. 41 N., R. 14 E., sec. 36, Mount Diablo Baseline and Meridian.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Roxanne Reimer
P.O. Box 220
Cedarville, CA 96104
530-233-8851
Roxanne.Reimer@usda.gov
Last Updated: 8/31/2022