Pinecrest Interior Healthy Forest Restoration
Fuel reduction on 780 acres within the urban interface around the community of Pinecrest. Treatments would include thinning, pile burning, meadow and riparian restoration and manual noxious weed removal.
Project Summary
Location Summary:
Pinecrest
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/29/2008 |
Objection Period Start | 04/03/2009 |
Decision | 05/2009 (Estimated) |
Implementation | 06/2009 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Hfra Title I: Wildland-Urban Interface
Lead Management Unit:
Summit Ranger District
Notice and Comment Regulation:
218
Project Purpose:
Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Completed
Project Decision Information
Pinecrest Interior Healthy Forest Restoration
Decision Signed Date: 05/18/2009
Pinecrest Interior Healthy Forest Restoration
Decision Signed Date: 05/18/2009
Forests:
Stanislaus National Forest
Districts:
Summit Ranger District
States:
California
Counties:
Tuolumne
Legal Land Description:
Sec 14-15, 21-23, 28-29 T4N R18E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Maria Benech
#1 Pinecrest Lake Road
Pinecrest, CA 95364
209-965-3434
mbenech@fs.fed.us
Last Updated: 1/30/2012