Hammill Canyon Meadow #7 Restoration
Using hand tools only, remove large wood debris from stream channel to re-establish original channel as the main channel. Place large wood debris in headcut to stabilize.
Project Summary
Location Summary:
Furthest upstream meadow along Herring Creek in Hammill Canyon
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/22/2011 |
Decision | 06/2011 (Estimated) |
Implementation | 07/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Summit Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management
Project Activity:
Species Habitat Improvements; Watershed Improvements
Current Status:
Completed
Project Decision Information
Hammill Canyon Meadow #7 Restoration
Decision Signed Date: 06/18/2011
Forests:
Stanislaus National Forest
Districts:
Summit Ranger District
States:
California
Counties:
Tuolumne
Legal Land Description:
Sec 21 T5N R19E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tracy Weddle
#1 Pinecrest Lake Road
Pinecrest, CA 95364
209-965-3434 x5321
tweddle@fs.fed.us
Last Updated: 7/6/2011