Arnold Rim Trail Cedar Center Connection Bikeway
Paved pedestrian/bike trail (non-motorized) connecting the Cedar Center (Oak Court) to Pine Drive and a dirt trail connecting the paved trail to the Arnold Rim Trail.
Project Summary
Location Summary:
Arnold, CA
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/01/2011 |
| Comment Period | 09/04/2012 |
| Decision | 10/2012 (Estimated) |
| Implementation | 11/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Calaveras Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Arnold Rim Trail Cedar Center Connection Bikeway
Decision Signed Date: 10/31/2012
Legal Notice Date: 11/05/2012
Forests:
Stanislaus National Forest
Districts:
Calaveras Ranger District
States:
California
Counties:
Calaveras
Legal Land Description:
Sec 30 T5N R15E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Patti Clarey
5519 Highway 4
Hathaway Pines, CA 95233
209-795-1381 Ext 315
pclarey@fs.fed.us
Last Updated: 11/6/2012