Coyote Meadow Restoration
Stabilize 3 headcuts in meadow and re-route trail away from stream and wet portion of meadow.
Project Summary
Location Summary:
Coyote Meadow adjacent to Cooper Meadow Trail (20E15) between the Cooper Meadow Trailhead and the Emigrant Wilderness
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/01/2013 |
| Decision | 02/2015 (Estimated) |
| Implementation | 08/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Summit Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements; Trail Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
Coyote Meadow Restoration
Decision Signed Date: 02/06/2015
Forests:
Stanislaus National Forest
Districts:
Summit Ranger District
States:
California
Counties:
Tuolumne
Legal Land Description:
Sec 34 T5N R19E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tracy Weddle
#1 Pinecrest Lake Road
Pinecrest, CA 95364
209-965-3434 x5321
tweddle@fs.fed.us
Last Updated: 2/9/2015