GAOA Campground/Day Use Site Toilet Replacement and Accessibility Upgrades
Replacement of existing vault and/or flush restroom facilities at the Lake Alpine Campground, Lake Alpine Boat Launch, Pacific Valley Campground, Highland Lake Campground and Cherry Lake Boat Ramp.
Project Summary
Location Summary:
Lake Alpine Campground, Lake Alpine Boat Ramp, Pacific Valley Campground, Highland Lakes Campground, Cherry Lake Boat Ramp
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/19/2022 |
Decision | 07/2022 (Estimated) |
Implementation | 08/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Stanislaus National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction
Current Status:
Completed
Project Decision Information
GAOA Campground/Day Use Site Toilet Replacement and Accessibility Upgrades
Decision Signed Date: 07/21/2022
Forests:
Stanislaus National Forest
Districts:
Calaveras Ranger District; Groveland Ranger District
States:
California
Counties:
Tuolumne
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kathryn Baker
19777 Greenley Road
Sonora, CA 95370
2092886335
Kathryn.Baker@usda.gov