Road 1106 Relocation
The proposal is to reroute Road 1106 by constructing approximately 500 feet of new road, remove a temporary bridge over Sulfur Creek and associated road fill from the Sulfur Creek floodplain, and decommission approximately 1/3 mile of existing road 1106.
Project Summary
Location Summary:
1 to 1.5 miles west of the south end of Baker Lake
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/17/2009 |
Comment Period | 06/16/2010 |
Decision | 07/2010 (Estimated) |
Implementation | 08/2010 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mt Baker Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Road Management
Project Activity:
Road Decommissioning; Road Improvements/Construction; Travel Management
Current Status:
Completed
Project Decision Information
Road 1106 Relocation
Decision Signed Date: 07/20/2010
Legal Notice Date: 07/21/2010
Forests:
Mt Baker-Snoqualmie National Forest
Districts:
Mt Baker Ranger District
States:
Washington
Counties:
Whatcom
Legal Land Description:
T 37 N, R 8 E, SW corner of section 25
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Don Gay
810 State Route 20
Sedro-Woolley, WA 98294
360-854-2632
dgay@fs.fed.us
Last Updated: 7/21/2010