White Chuck Bench Trail Repair and Reconstruction
Repair and reconstruct the White Chuck Bench Trail (#731) that was damaged in both the 2003 and 2007 floods. Repair work includes relocation and reconstruction at multiple locations from several hundred feet to over 1 mile in length.
Project Summary
Location Summary:
Lower White Chuck River valley
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/26/2010 |
| Decision | 04/2015 (Estimated) |
| Implementation | 05/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Darrington Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
White Chuck Bench Trail Relocation
Decision Signed Date: 04/23/2015
Forests:
Mt Baker-Snoqualmie National Forest
Districts:
Darrington Ranger District
States:
Washington
Counties:
Snohomish
Legal Land Description:
T31N R11E Sec 15, 16, 17 and 18
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Bridget Wisniewski
1405 Emens Avenue North
Darrington, WA 98241
360-436-1155
bwisniewski@fs.fed.us
Last Updated: 4/23/2015