Middle Fork Trail 1003 Reroute
Construct approx. 0.5 miles of new trail beginning near the 1 mile marker, providing a route around the April 2018 landslide area that destroyed about 300 feet of trail. The trail would be suitable for existing uses, including stock and bikes.
Project Summary
Location Summary:
The project site begins at approximately the 1 mile point on the Middle Fork Trail. It can be accessed via the Middle Fork Trailhead, near North Bend, WA.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/05/2019 |
Decision | 03/2020 (Estimated) |
Implementation | 04/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Snoqualmie Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Developed Site Management; Trail Management
Current Status:
Completed
Project Decision Information
Middle Fork Trail 1003 Reroute
Decision Signed Date: 03/02/2020
Forests:
Mt Baker-Snoqualmie National Forest
Districts:
Snoqualmie Ranger District
States:
Washington
Counties:
King
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Brian McNeil
902 S.E. North Bend Way, Bldg 1
North Bend, WA 98045
425-888-8769
comments-pacificnorthwest-mtbaker-snoqualmie-snoqualmie@fs.fed.us
Last Updated: 3/5/2020