Cascade Crossing Transmission Project
Portland General Electric proposes to construct, maintain, and operate a 500 kV, single-circuit transmission line that would cross 1.2 miles of the Mt. Hood National Forest.
Project Summary
Location Summary:
Boardman, Oregon to Pine Grove, Oregon
Project Milestones:
Milestone | Date |
---|---|
NOI in Federal Register | 06/01/2010 |
DEIS NOA in Federal Register | 10/2013 (Estimated) |
FEIS NOA in Federal Register | 05/2014 (Estimated) |
Decision | 10/2014 (Estimated) |
Implementation | 03/2017 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mt. Hood National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission
Current Status:
Cancelled
Forests:
Mt. Hood National Forest
Districts:
Clackamas River Ranger District
States:
Oregon
Counties:
Wasco
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kristy Boscheinen
16400 Champion Way
Sandy, OR 97055
503-668-1645
kboscheinen@fs.fed.us
Last Updated: 6/21/2013