AeroVironment Electric Vehicle Charging Station
Construction of an electric vehicle charging station in the Skibowl West parking lot
Project Summary
Location Summary:
Skibowl West Ski Resort
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/15/2013 |
Comment Period | 05/30/2013 |
Decision | 07/2013 (Estimated) |
Implementation | 08/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Zigzag Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Electric Vehicle charging Station at Skibowl West
Decision Signed Date: 07/11/2013
Electic Vehicle Charging Station at Skibowl West
Decision Signed Date: 07/11/2013
Legal Notice Date: 07/18/2013
AeroVironment Electric Vehicle Charging Station
Decision Signed Date: 07/11/2013
Legal Notice Date: 07/18/2013
Forests:
Mt. Hood National Forest
Districts:
Zigzag Ranger District
States:
Oregon
Counties:
Clackamas
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Leanne Veldhuis
70220 E. Highway 26
Zigzag, OR 97049
503-622-2030
lveldhuis@fs.fed.us
Last Updated: 9/30/2013