Portland General Electric (PGE) Buried Line Replacement near Summit Ski Area CE
In order to provide safe and reliable power, PGE has proposed to replace a current buried powerline that is failing due to aging. This new line (about 1,300 feet in length) will be installed adjacent to the existing line, which will remain in ground.
Project Summary
Location Summary:
The proposed replacement powerline is near the Summit Ski Area.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/29/2015 |
| Decision | 09/2015 (Estimated) |
| Implementation | 09/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Zigzag Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Portland General Electric (PGE) Buried Line Replacement near Summit Ski Area CE
Decision Signed Date: 09/04/2015
Forests:
Mt. Hood National Forest
Districts:
Zigzag Ranger District
States:
Oregon
Counties:
Clackamas
Legal Land Description:
T3S R8E Section SW13 and NW24
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
MaryEllen Fitzgerald
70220 E. Highway 26
Zigzag, OR 97049
503-622-3191ext 625
mfitzgerald@fs.fed.us
Last Updated: 9/21/2015