Pollywog Insect and Disease Project
This project will reduce the risk of landscape level disturbance and increase forest resiliency to insect and disease. This project would reduce stand density on about 2,600 acres using mechanical and non-mechanical treatments.
Project Summary
Location Summary:
The project is located immediately adjacent to The Dalles Municipal Watershed within the Eightmile Watershed.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/11/2020 |
Decision | 06/2020 (Estimated) |
Implementation | 07/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.3 (5)
Special Authority:
Hfra Title Vi: Insect And Disease Projects
Lead Management Unit:
Barlow Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products; Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels); Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Pollywog Insect and Disease Project
Decision Signed Date: 06/23/2020
Forests:
Mt. Hood National Forest
Districts:
Barlow Ranger District
States:
Oregon
Counties:
Wasco
Legal Land Description:
T1S R11E Sections 15, 21-24, 26-29, & 31-33. T2S R11E Sections 5 & 6.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kameron Sam
780 NE Court Street
Dufur, OR 97021
541-467-5101
kcsam@fs.fed.us
Last Updated: 6/24/2020