2013 Special Use Authorization Projects (reissue 9 authorizations)
Issue 9 authorizations to replace existing and/or expired authorizations for: water transmission lines, roads, and livestock areas.
Project Summary
Location Summary:
Various locations within the Central Coast Ranger District--Oregon Dunes National Recreation Area.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/30/2013 |
| Decision | 12/2014 (Estimated) |
| Implementation | 01/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Central Coast Ranger District/Oregon Dunes National Recreation Area
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Special Use Authorizations Multi-Year Permits
Decision Signed Date: 12/22/2014
Forests:
Siuslaw National Forest
Districts:
Central Coast Ranger District/Oregon Dunes National Recreation Area
States:
Oregon
Counties:
Benton; Coos; Douglas; Lane; Lincoln
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
John Harper
PO Box 400
Waldport, OR 97394-0400
541-271-6023 or 541-271-6000
comments-pacificnorthwest-siuslaw-centralcoast@fs.fed.us
Last Updated: 12/30/2014