3 Rivers Restoration & Access
Multiple failed bridges on FSR 2285 has cutoff access to Forest Service and Private land. Construct approximately 800 ft. of road from end of FSR 1410 to FSR 2285 to allow Terrestrial and Aquatic restoration and Private access. 36 CFR 220.6(e)(6).
Project Summary
Location Summary:
Road Access- Hwy.22 to FSR 1491 to FSR 1410 (additionally see Legal Land Description).
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/07/2017 |
Decision | 07/2019 (Estimated) |
Implementation | 08/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hebo Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management
Project Activity:
Species Habitat Improvements; Watershed Improvements
Current Status:
Completed
Project Decision Information
3 Rivers Restoration & Access
Decision Signed Date: 07/17/2019
Forests:
Siuslaw National Forest
Districts:
Hebo Ranger District
States:
Oregon
Counties:
Yamhill
Legal Land Description:
Section 26, 34, & 35, T. 4 S., R. 9 W., and Section 3, T. 5 S., R. 9 W., Yamhill county, Willamette Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Alexander Wickham
31525 Hwy 22
Hebo, OR 97122
503-392-5136
alexander.wickham@usda.gov
Last Updated: 7/25/2019