West Fork 8th Creek OHV Trail Bridge Replacement
The purpose of this project is to rebuild the West Fork 8th creek trail bridge. The bridge has failed and collapsed. There is a need for the bridge to be replaced to enhance user safety and protect natural resources.
Project Summary
Location Summary:
T20s, R4e, Section 7
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/11/2024 |
Decision | 06/2025 (Estimated) |
Implementation | 08/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Middle Fork Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
West Fork 8th Creek OHV Trail Bridge Replacement Decision Memo
Decision Signed Date: 06/03/2025
Forests:
Willamette National Forest
Districts:
Middle Fork Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kevin Rowell
46375 Highway 58
Westfir, OR 97492
541-782-5305
kevin.a.rowell@usda.gov
Last Updated: 6/3/2025