Carmen Reservoir Bridge Replacement
Replace the current poor condition bridge, with a new bridge that meets current safety standards. The bridge will be lengthened to move abuttments farther from the river and restore riparian function.
Project Summary
Location Summary:
The project is located on Forest Road 2600750 adjacent to Carmen Diversion Reservoir
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/24/2010 |
Decision | 07/2010 (Estimated) |
Implementation | 07/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (7), 36 Cfr 220.6(E)(7)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Willamette National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Wildlife, Fish, Rare Plants; Special Use Management
Project Activity:
Species Habitat Improvements; Road Maintenance
Current Status:
Completed
Project Decision Information
Carmen Reservoir Bridge Replacement Project
Decision Signed Date: 07/06/2010
Forests:
Willamette National Forest
Districts:
McKenzie River Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
Township 14 South, Range 7 East, Section 20
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dave Kretzing
3106 Pierce Parkway
Springfield, OR 97477
541-822-7227
dkretzing@fs.fed.us
Last Updated: 9/17/2010