BPA Hills Creek Pole Replacement Project
Two poles installed on the BPA powerline between Oakridge and Hills Creek Dam in 1962 have major decay and need to be replaced. In addition, BPA needs to re-open the spur roads that access the line in order to improve response time for line outages.
Project Summary
Location Summary:
On the BPA powerline between Oakridge and Hills Creek Dam.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/01/2011 |
Decision | 08/2011 (Estimated) |
Implementation | 08/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Middle Fork - Inactive Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations; Facility Maintenance
Current Status:
Completed
Project Decision Information
Bonneville Power Administration Hills Creek Power Pole Replacement Project
Decision Signed Date: 08/01/2011
Forests:
Willamette National Forest
Districts:
Middle Fork - Inactive Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
T21S, R3E, Section 22
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shari Monson
46375 Highway 58
Westfir, OR 97492
541-225-6424
smonson@fs.fed.us
Last Updated: 8/2/2011