Castle Project
To commercially thin three stands; 30, 16, and 10 acres. These stands are second growth with an average age of 40 years. The project will be harvested with ground base and skyline equipment using existing skid roads as much as possible.
Project Summary
Location Summary:
Located on Forest road 2639480 just past the private land.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/24/2012 |
Comment Period | 06/05/2012 |
Decision | 08/2012 (Estimated) |
Implementation | 09/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (12), 36 Cfr 220.6(E)(12)
Special Authority:
Not Applicable / Other
Lead Management Unit:
McKenzie River Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Forest Products
Project Activity:
Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Castle Project
Decision Signed Date: 08/13/2012
Forests:
Willamette National Forest
Districts:
McKenzie River Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
Section 28 and 29; T16S, R5E; W.M. Lane Co.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shadie Nimer
57600 McKenzie Hwy
McKenzie Bridge, OR 97413
541-822-7271
snimer@fs.fed.us
Last Updated: 8/28/2012