AT&T/Cingular Wolf Mt. Tower Replacement
Velocitel requests replacement of the existing tower at Wolf Mt., which is failing. The new tower will be the same height at the existing tower and in the same location. Existing footings would be replaced. Work would be in already disturbed ground.
Project Summary
Location Summary:
Wolf Mountain
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/17/2012 |
Comment Period | 12/17/2012 |
Decision | 07/2013 (Estimated) |
Implementation | 07/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Middle Fork - Inactive Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
AT&T/Cingular Wireless Wolf Mt. Tower Replacement Project
Decision Signed Date: 07/01/2013
Legal Notice Date: 07/05/2013
Forests:
Willamette National Forest
Districts:
Middle Fork - Inactive Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
T22S, R5E, SW 1/4 of Section 33
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shari Monson
46375 Highway 58
Westfir, OR 97492
541-782-5243
smonson@fs.fed.us
Last Updated: 7/15/2013