French Pete Creek Crossing Repair
The proposed project would harden the creek crossing at mile 2.1 of the French Pete Creek Trail (FS Trail 3311) to mitigate erosion.
Project Summary
Location Summary:
Mile 2.1 of the French Pete Creek Trail (FS Trail 3311) in the Three Sisters Wilderness
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/22/2013 |
Decision | 06/2013 (Estimated) |
Implementation | 10/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
McKenzie River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management; Wilderness Management
Current Status:
Completed
Project Decision Information
French Pete Creek Crossing Repair
Decision Signed Date: 06/14/2013
Forests:
Willamette National Forest
Districts:
McKenzie River Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
T18S, R5E, Sec. 3
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Edward Cross
57600 McKenzie Hwy
McKenzie Bridge, OR 97413
541-822-7231
etcross@fs.fed.us
Last Updated: 12/10/2019