Re-route of Road 2041
Relocate about 500-600 feet of road 2041 where its alignment has shifted due to an active slide. Replace and realign 5-6 foot culvert. Remove rock from the abandoned portion of road and use on relocated portion. Decommission abandoned roadbed.
Project Summary
Location Summary:
Milepost 11.1 on the 2041 road.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/05/2015 |
Decision | 07/2015 (Estimated) |
Implementation | 07/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (12), 36 Cfr 220.6(E)(12); 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (20), 36 Cfr 220.6(E)(20)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sweet Home Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Decommissioning; Road Maintenance; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Re-route of Road 2041
Decision Signed Date: 07/07/2015
Forests:
Willamette National Forest
Districts:
Sweet Home Ranger District
States:
Oregon
Counties:
Linn
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Daniel Matthews
4431 Highway 20
Sweet Home, OR 97386
541-367-3812
danielwmatthews@fs.fed.us
Last Updated: 12/29/2015