EWEB Load Bank
EWEB is proposing to install a fenced area for the Load Bank with associated transmission line poles within an area of approximately 2.5 acres. Approximately 237 Trees would be removed and used exclusively for aquatic restoration projects.
Project Summary
Location Summary:
The proposed project is located within the Upper McKenzie Watershed on the McKenzie River Ranger District of the Willamette National Forest. The proposed project area is located off FS Road 2600730.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/12/2022 |
Decision | 10/2022 (Estimated) |
Implementation | 10/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
McKenzie River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Hydropower
Current Status:
Completed
Project Decision Information
EWEB Load Bank
Decision Signed Date: 10/13/2022
Forests:
Willamette National Forest
Districts:
McKenzie River Ranger District
States:
Oregon
Counties:
Linn
Legal Land Description:
T.15S., R.6E., Section 1, Willamette Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shane Kamrath
57600 McKenzie Hwy
McKenzie Bridge, OR 97413
541-822-7233