EWEB Carmen Campus improvements
EWEB is proposing to install two new manufactured homes, one site built garage, associated wastewater drain fields, and underground utilities. Additionally we plan to remove an existing building and replace it with an larger one.
Project Summary
Location Summary:
Location is at the EWEB Carmen-Smith Hydroelectric Project Carmen Campus
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/18/2023 |
Decision | 07/2023 (Estimated) |
Implementation | 09/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Willamette National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Facility Improvements/Construction; Hydropower; Facility Maintenance
Current Status:
Completed
Project Decision Information
EWEB Carmen Campus improvements
Decision Signed Date: 07/17/2023
Forests:
Willamette National Forest
Districts:
McKenzie River Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shane Kamrath
3106 Pierce Parkway
Springfield, OR 97477
541-822-7233
shane.kamrath@usda.gov