Entergy Amendment #37 - Saline Lake Reliability Project
New 20 KW line from a private tract in Section 26 T11N-R5W - along the Coldwater Rd, south along Lakeshore Dr to Lyles Camp and north along Lakeshore Dr. to Keyhole Rd. This project would more evenly distribute power needs to an overburdened system.
Project Summary
Location Summary:
Along Coldwater, Lakeshore Dr., Keyhole and Lylse Camp Rds, in Winn Parish, LA
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/07/2012 |
| Comment Period | 11/07/2012 |
| Decision | 10/2013 (Estimated) |
| Implementation | 11/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Winn Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Entergy Amendment #37 Saline Reliability Project
Decision Signed Date: 10/18/2013
Forests:
Kisatchie National Forest
Districts:
Winn Ranger District
States:
Louisiana
Counties:
Winn
Legal Land Description:
Sec. 22, 26, 27 and 28 of T11N-R05W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Barbara Poole
12319 U.S. Highway 84 West
Winnfield, LA 71483
318-682-4664
blpoole@fs.fed.us
Last Updated: 12/30/2013