Eagle Nest Electric Power line Installation
Run approximately 880 feet of new electric power line from existing power line by burying line 2 feet deep for the purpose of powering live video cameras and a DVT unit so that the public can watch a live eagle nest.
Project Summary
Location Summary:
US Forest Service - Kincaid Reservoir Recreation Area southwest of beach area.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/19/2014 |
| Decision | 12/2014 (Estimated) |
| Implementation | 01/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Calcasieu Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Wildlife, Fish, Rare Plants
Project Activity:
Developed Site Management; Dispersed Recreation Mgmt.
Current Status:
Completed
Project Decision Information
Eagle Nest Electric Power Line Installation Project
Decision Signed Date: 12/05/2014
Forests:
Kisatchie National Forest
Districts:
Calcasieu Ranger District
States:
Louisiana
Counties:
Rapides
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Steve Shively
9912 Hwy 28 West
Boyce, LA 71409
318-793-9427
comments-southern-kisatchie-calcasieu@fs.fed.us
Last Updated: 12/5/2014