Kisatchie Bayou Camp Rehabilitation
Kisatchie Bayou Camp Rehabilitation would include, convert 8 over night campsites to day-use sites, install concrete stairs for bayou access, install rip-rap for streambank stabilization, relocate toilet away from eroding bank, reconfigure parking.
Project Summary
Location Summary:
Township 5 North, Range 7 West, Section 4
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/25/2019 |
Decision | 06/2019 (Estimated) |
Implementation | 06/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (5), 36 Cfr 220.6(D)(5)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Kisatchie Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Dispersed Recreation Mgmt.
Current Status:
Completed
Project Decision Information
Kisatchie Bayou Camp Rehabilitation
Decision Signed Date: 06/07/2019
Forests:
Kisatchie National Forest
Districts:
Kisatchie Ranger District
States:
Louisiana
Counties:
Natchitoches
Legal Land Description:
Township 5 North, Range 7 West, Section 4
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kelly Boles
229 Dogwood Park Road
Provncal, LA 71468
318-472-1840
kboles@fs.fed.us
Last Updated: 6/7/2019