Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/02/2010 |
Decision | 12/2010 (Estimated) |
Implementation | 06/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Eagle River-Florence Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Special Use Authorizaton for City of Eagle River Bike Trail
Decision Signed Date: 12/20/2010
Forests:
Chequamegon / Nicolet National Forest
Districts:
Eagle River-Florence Ranger District
States:
Wisconsin
Counties:
Vilas
Legal Land Description:
T40N, R10E, S28
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeff Herrett
1247 E. Wall St.
Eagle River, WI 54521
715-479-2827
jherrett@fs.fed.us
Last Updated: 12/20/2010