Norvado Fiber Install
Proposal to install approximately 1.4 miles of underground fiber optic cable and associated equipment. All of the installation would be adjacent to existing roadways. This project would provide faster and more reliable internet service.
Project Summary
Location Summary:
T44N R7W Sections 26, 27, 34, & 35, Bayfield County, WI
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/09/2016 |
Decision | 03/2017 (Estimated) |
Implementation | 03/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Washburn Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Norvado Fiber Install
Decision Signed Date: 03/24/2017
Forests:
Chequamegon / Nicolet National Forest
Districts:
Washburn Ranger District
States:
Wisconsin
Counties:
Bayfield
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jonathan McNeill
113 Bayfield St. East
Washburn, WI 54891
(715) 762-5154
jdmcneill@fs.fed.us