WPS Forest County STH 32 LKLN 2023
Replacing the old wire with new wire along Hwy 32.
Project Summary
Location Summary:
Legal is Township 34 North, Range 15 east, Section 21. Along Highway 32.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/07/2023 |
Decision | 08/2023 (Estimated) |
Implementation | 08/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lakewood-Laona Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
WPS Forest County STH 32 LKLN 2023
Decision Signed Date: 08/02/2023
Forests:
Chequamegon / Nicolet National Forest
Districts:
Lakewood-Laona Ranger District
States:
Wisconsin
Counties:
Forest
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Casey Swanson
15085 State Road 32
Lakewood, WI 54138
715-362-1300
Casey.Swanson@usda.gov
Last Updated: 8/9/2023