Forest Road 182 Segment Reroute
A 1.22-mile reroute is proposed to improve the operation of the road and avoid a wetland that is regularly in need of gravel application.
Project Summary
Location Summary:
Forest Road 182 segment northeast of Clam Lake
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/19/2024 |
Decision | 05/2025 (Estimated) |
Implementation | 05/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Great Divide Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Decommissioning; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Forest Road 182 Segment Reroute
Decision Signed Date: 05/03/2025
Forests:
Chequamegon / Nicolet National Forest
Districts:
Great Divide Ranger District
States:
Wisconsin
Counties:
Ashland
Legal Land Description:
T43N R4@ Sections 22, 23, 26, 27
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Eric Lynch
N22223 Hwy. 13
Gidden, WI 54527
715-762-5137
eric.lynch@usda.gov
Last Updated: 5/14/2025