Norvado Fiber Optic Installation
Installation of underground fiber optic cable in portions of National Forest System land along State Highway 77, County Road S, Sams Lane, and Forest Roads 164, 174, 308, and 1661.
Project Summary
Location Summary:
Right of Ways for State Highway 77, County Road S, Sams Lane, Forest Roads 164, 174, 308, and 161 south of Clam Lake, WI.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/27/2024 |
Comment Period | 05/15/2024 |
Decision | 07/2024 (Estimated) |
Implementation | 07/2024 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chequamegon / Nicolet National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Norvado Fiber Optic Installation
Decision Signed Date: 07/03/2024
Forests:
Chequamegon / Nicolet National Forest
Districts:
Great Divide Ranger District
States:
Wisconsin
Counties:
Sawyer
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nicole Molitor
500 Hanson Lake Road
Rhinelander, WI 54501
715-638-0272
nicole.g.molitor@usda.gov
Last Updated: 7/3/2024