Reservoir Operating Plan Evaluation (ROPE) Study
Operation of Federal dams and coordination with operators of non-Federal dams in the headwaters of the Mississippi River area between Bemidji and St. Paul
Project Summary
Current Status:
Completed
Location Summary:
Upper Mississippi River between Bemidji and St. Paul
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 12/12/2003 |
| DEIS NOA in Federal Register | 08/26/2008 |
| FEIS NOA in Federal Register | 10/02/2009 |
| Decision | 06/2012 (Estimated) |
| Implementation | 06/2010 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chippewa National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Watershed Management; Recreation Management; Wildlife, Fish, Rare Plants
Project Activity:
Watershed Improvements
Project Decision Information
Reservoir Operating Plan Evaluation (ROPE) Study
Decision Signed Date: 06/14/2012
Legal Notice Date: 08/18/2012
Forests:
Chippewa National Forest
Districts:
Chippewa National Forest All Units
States:
Minnesota
Counties:
Beltrami; Cass; Itasca
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Luke Rutten
200 Ash Avenue NW
Cass Lake, MN 56633
218-335-8666
lrutten@fs.fed.us
Last Updated: 9/13/2012