Bud Lake Woodcock Habitat Improvement Project
Maintenance and improvement of 12 acres of woodcock habitat in the Portage Creek watershed. This includes shearing decadent alder and allowing it to regenerate. This project would be completed in winter under frozen ground conditions.
Project Summary
Current Status:
Completed
Location Summary:
South of Hwy 2 and north of Bud Lake on the north end of the Walker RD.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/21/2012 |
| Comment Period | 11/21/2012 |
| Decision | 02/2013 (Estimated) |
| Implementation | 02/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Walker Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Project Decision Information
Bud Lake Woodcock Habitat Improvement Project
Decision Signed Date: 02/20/2013
Legal Notice Date: 02/20/2013
Bud Lake Woodcock Habitat Improvement Project
Decision Signed Date: 02/20/2013
Legal Notice Date: 02/20/2013
Forests:
Chippewa National Forest
Districts:
Walker Ranger District
States:
Minnesota
Counties:
Cass
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Cory Mlodik
201 Minnesota Ave E.
Walker, MN 56484
307-276-5808
corymlodik@fs.fed.us