Miss Bigfork Watershed Restoration Project
Removal of the Sugar Lake impoundment to restore wetlands.
Project Summary
Current Status:
Completed
Location Summary:
Sugar Lake impoundment west of Lake Winnie. Within the Leech Lake Reservation.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/01/2019 |
| Decision | 08/2019 (Estimated) |
| Implementation | 08/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (20), 36 Cfr 220.6(E)(20)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Blackduck Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management
Project Activity:
Watershed Improvements
Project Decision Information
Miss Bigfork Watershed Restoration Project
Decision Signed Date: 08/23/2019
Forests:
Chippewa National Forest
Districts:
Blackduck Ranger District
States:
Minnesota
Counties:
Cass; Itasca
Legal Land Description:
Sugar lake Impoundment: T146 R29 Sec 22.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Eric Raitanen
417 Forestry Drive
Blackduck, MN 56630
218-246-3475
ericraitanen@fs.fed.us
Last Updated: 8/26/2019